Sunday, October 25, 2026

ORACLE BLOOM AND YUCCA WANT TO USE TAXPAYER DOLLARS TO SUBSIDIZE MAINTENANCE OF THE FUEL CELL POWER PLANT

Yucca has submitted a new air permit application where they will install 2,462 megawatts of Bloom fuel cells but only operate with a maximum output of 1,600 megawatts. This is a capacity factor just under 65% or put more simply the size of the power station is overbuilt by 53.9%. Bloom fuel cells degrade over time and require service and maintenance that Bloom charges to its customers. When new fuel cells are installed, the IRS grants the owner of the fuel cells a 30% investment tax credit on the fully installed cost of the fuel cells. Therefore, if the fuel cells have an installed cost of $4.5 million per megawatt, taxpayers pay for $1.5 million per megawatt via the 30% investment tax credit. In addition to the investment tax credit, taxpayers will also pay 25% of the extra $4.5 million per megawatt through the deduction of accelerated depreciation of the larger unnecessary power plant. The extra 862 megawatts of fuel cells that Oracle, Bloom and Yucca want to install will cost US taxpayers something like $2.133 billion even though these fuel cells are essentially redundant and are simply there to lessen wear and tear on the power plant and save the owner on maintenance costs. Bloom will need less maintenance on fuel cells that only need to achieve 65% capacity factor. They may even run degraded fuel cells that are less efficient and yet meet the guaranteed level of 1,600 megawatts. Yucca and hence Oracle will save on maintenance costs each year. Interestingly Bloom typically guarantees clients a 95% capacity factor and in the case of the Jupiter project this 95% guarantee would mean only an addition of 84 megawatts over and above the 1,600 megawatts of output would be needed for the guaranteed nameplate capacity of the power plant. Yucca, Oracle and Bloom are trying to have TAXPAYERS foot the HUGE maintenance and service bill that otherwise they would have had to bear. This is OUTRAGEOUS and must not happen. Bloom is trying to pull a similar story in Vineland New jersey where they intend to install 328 megawatts of fuel cells at a data center but only guarantee 250 megawatts of available power. The Vineland case is a 75% capacity factor or a 31.2% over build. The New Mexico RIPOFF is higher than New Jersey, but both cases are INSANE and a waste of TAXPAYER DOLLARS. Let’s go back to Delaware back in 2019 when Bloom allowed two power stations to become dilapidated in only six years and then applied for “minor maintenance” permits for the power stations. But instead of minor maintenance Bloom and their tax equity partners Southern Power and Assured Guaranty fully replaced the power stations with new Bloom fuel cells and took $75 million in Investment tax credits from taxpayers. Bloom should have borne maintenance costs but instead taxpayers subsidized additional sales revenue on which they enjoyed a margin. Note that Lindsay Leveen has informed the IRS and the FBI of the tax fraud in Delaware. So far, the IRS has done nothing. The Delaware power stations total only 27.5 megawatts. Jupiter wants to install a power station that is 80 times larger than Delaware BLOOMDOGGLE in New Mexico. Lindsay Leveen wishes to inform authorities in New Mexico including the AG and the Governor that this fleecing of US taxpayers will happen if a 2,462-megawatt power plant is allowed to be built for project Jupiter. There are numerous environmental reasons to oppose this plant but ripping off taxpayers to avoid maintenance costs takes the cake. I implore the N.M. DOJ to investigate this unwarranted taking of tax credits.

Sunday, May 31, 2026

BLOOM CREATES A LOT OF SOLID WASTE WHEN GENERATING DIRTY POWER

-----------------------------------------------------------------------------------------------I reviewed the permit application for the 2,465 Megawatt power station Bloom intends to build for Oracle in New Mexico. It looks like Bloom creates 0.75 pounds of solid waste per Megawatt Hour of power generated. The solid waste is filled with with hazards like Benzene, Lead, Chromium and Arsenic within the waste. -----------------------------------------------------------------------------------------------THIS IS A LOT OF WASTE -----------------------------------------------------------------------------------------------If you do a Google search on Bloom and Solid Waste, Google LIES that Bloom has very little solid waste. Google helped launch Bloom back in 2009 and Google is an UNTRUSTWORTHY source for information on the BLOOMDOGGLE.

Saturday, May 16, 2026

BLOOM ENERGY HAS HUGE PROBLEMS

Bloom is the darling of Wall Street and Jim Cramer of Mad Money worships them. But Bloom has a history of GREENWASHING. That history is going to come back to bite them in the ass. In 2018 they submitted permit applications in Delaware to rebuild two power stations. They told Delaware DNREC they would emit 700 pounds of CO2 per megawatt hour and 0.0017 pounds of NOX per megawatt hour. DNREC set limts on the hourly and rolling twelve month periods based on these values. Now it turns out that the NOX emissions are far higher and Bloom admits to 0.003 pounds of NOX per megawatt hour some 76% higher than in the permit. The CO2 emissions are approximately 820 pounds per megawatt hour and this is 18% higher than in the permits. But the NOX is the Bloom weed killer like ROUNDUP! ----------------------------------------------------------------------------------------- Bloom has generated far too many megawatt hours over the past years and has overcharged Delmarva Ratepayers for the subsidy these ratepayers pay bassed on $166.81 per megawatt hour. I estimate the overcharge to ratepayers is approximately $150 million. I have alerted the FBI and EPA CID of the overcharge. No doubt there is a watertight case for ratepayers to get their money back and for the EPA to levy fines and award consequential damages. ------------------------------------------------------ Interestingly in a new permit application Bloom recenly made in New Mexico for the power plant at an AI Data Center called Jupiter they admitted to emissions of 941 pounds of CO2 per megawatt hour and NOX emissions of 0.00345 pounds per megawatt hour. The NOX emission rate is now twice as high as in the Delaware permits. I have forwarded this to the EPA CID. ----------------------------------------------------------------------- It will be interesting to see if Bloom is allowed by the FBI and EPA to sweep NOX under the rug. The corrupt EPA under Jackson, McCarthy, Pruitt and Wheeler let Bloom dump HAZMAT with Lead, Chromium, Arsenic and Benzene in common landfills. How do I know this. I was the tipster to the EPA. I sued the EPA in Leveen V The United States ----------------------------------------------------- Remember that GREEN LIES MATTER

Wednesday, December 10, 2025

WHAT FRACTION OF BLOOM ENERGY'S PRODUCTION CAPACITY IS USED FOR REPLACEMENT OF OLD STACKS?

I HAVE ASKED THE ANALYSTS WHO FOLLOW BLOOM TO ASK THE CEO A SIMPLE SINGLE QUESTION. WHAT FRACTION OF BLOOM ENERGY'S PRODUCTION CAPACITY IS USED FOR REPLACEMENT OF OLD STACKS? BLOOM HAS 1,500 MEGAWATTS OF FUEL CELLS INSTALLED. IF THE STACKS ONLY LAST 2 YEARS AS REAL DATA FROM NYSERDA SUGGEST THEY NEED 750 MEGAWATTS PER YEAR OF STACK REPLACMENT. BLOOM GAS PRODUCTION CAPACITY OF 1,000 MEGAWATTS PER YEAR. ON THIS BASIS THREE QUARTERS OF BLOOM'S CAPACITY TO PRODUCE FUEL CELLS IS USED UP BY REPLACING OLD STACKS THAT STOPPED FUNCTIONING BECAUSE OF ORDINARY DEGREDATION. IF THIS FRACTION IS THE REAL FRACTION THEN BLOOM INVESTORS WILL LOSE MONEY ON BUYING AN OVERHYPED AI STOCK. LET'S SEE IF THE WALL STREET ANALYSTS HAVE THE BALLS TO ASK THIS SIM[PLE QUESTION AT THE NEXT EARNINGS CALL? GREEN LIES MATTER

Friday, September 5, 2025

only a test

only a test

Saturday, February 17, 2024

BLOOM ENERGY CFO/PRESIDENT QUITS

Bloom Energy the largest ecofraud of the 21st century had terrible financial results and their CFO/PRESIDENT Quit. Joe Bidens two sons were part of the Bloomdoggle in Deal Away. I am still investigating if the BIG GUY was part of the scam on ratepayers and taxpayers for his friend John Doerr. Doerr is the OLIGARCH IN CHIEF OF SILLY CON VALLEY. Theranos was the Bloom of BLOOD and Bloom is the Theranos of Thermodynamics. The US SEC has protected Bloom because the SEC = Save Every Crook hashtag#GREENLIESMATTER

Saturday, February 10, 2024

AMERICAN INJUSTICE

There is no doubt that US has a two tiered justice system and certain polticians and billionaires are above the law. The BLOOM ENERGY BLOOMDOGGLE in Delaware opened my eyes long ago to how the EPA, FBI, SEC, FERC, FTC, and DOE protected PURE 100% FRAUD. Now the Special Counsel is claiming Joe Biden is Mentally UNFIT for prosecution for mishandling classified documents. Micheal Regan who heads the EPA is Thermodynamically UNFIT for his job. Gary Gensler who heads the SEC is morally UNFIT for his job. Willie Phillips who heads FERC is electrically UNFIT for his job. Lisa Khan who heads the FTC is commercially UNFIT for her job. And Jennifer Granholm who heads the DOE is totally UNFIT for her job. The entire BIDEN ADMINISTRATION is composed of MISFITS. GREEN LIES MATTER